An Australian icon in Busicut manufacture relocated their Melbourne operation to Sydney. To aviod running out of stock, The relocation hinged around pulling out and relocating one line at a time. This had the challange of working in a food production enviroment while dismantling and removing equipment and machinery from site.
​
M & M Autopak was engaged as the principle contractor looking after mechanical and Electrical disconnection, Transport and mechanical installation and Electrical control re-connection
This project had 8 mechanical/electrical tradesman working over a period of 20 weeks during 2016
.